What is the ideal soil density for the bulldozer productivity curve?
Refer to the initial conditions discussed in class.
Name one correction factor that affects bulldozer productivity.
We discussed multiple factors earlier in class.
What is a correction factor?
Think about how we adapt our estimates.
Correctly adjusting productivity for soil density decreases it.
Link your understanding back to soil conditions.
Estimate the hourly productivity if the original expectation is 120 m³/hour, but correction factors for soil density (0.85), poor visibility (0.75) and operator skill (0.70) have to be applied.
Multiply each correction factor by the initial productivity.
If a bulldozer's operational cost is 1600 rupees per hour, with a productivity of 40 bank m³/hour, calculate the unit cost per bank m³.
This is a basic division of costs by productivity.