What is a scraper?
Think about its role in construction.
What does a pusher do?
Consider its function in the operation of scrapers.
What rate of productivity is achieved with 5 scrapers?
Remember the specific scrapers output from class.
True or False: More scrapers always result in lower costs.
Reflect on the cost analysis we did.
Given 5 scrapers working for 8 hours, calculate daily productivity in bcm if the hourly production is 636.89.
Consider how many hours they operate together.
If production costs are ₹44.12 per bcm at 5 scrapers and the total volume required is 10,000 bcm, calculate the total cost involved.
Remember the link between cost per unit and total volume.
4 more questions in this section. Enroll free to practise them all.