4 cards from this section. Quick, good the night before a test.
Define the term 'Swell Factor'.
Think of how material volume changes when excavated.
What does cycle time encompass?
Consider all parts of a task completion for a machine.
What is the swell factor used for?
Recall its definition and purpose.
True or False: Cycle time includes only the loading and dumping time.
Remember what we discussed about the full operation time.
A project requires moving 1000 m³ of earth with a swell factor of 0.9. Calculate the bank volume needed.
Remember to convert loose to bank using the swell factor.
You have a scraper with a cycle time of 6 minutes and a pusher cycle time of 1.5 minutes. How many scrapers can one pusher sustain? Calculate and reflect on the operational impacts of this ratio.
Use the balance formula for your calculations.