What is the balance number of trucks if the truck cycle time is 39.5 and the loader cycle time is 5.5?
Use the formula: Balance Number = Truck Cycle Time / Loader Cycle Time.
If you have 6 trucks with a productivity of 12.53-meter cubes per hour, what is the total productivity?
Multiply the number of trucks by individual truck productivity.
What determines the balance number of trucks needed?
Review the formula for balance number.
True or False: Increasing the number of trucks beyond the balance number increases productivity without limit.
Consider how loader productivity caps overall output.
If your current operation uses 7 trucks but proposes to use 10 for a new project, analyze the potential productivity and cost outcomes. What would you recommend?
Calculate using the productivity limits of the loader.
Calculate the overall production cost for using 6 trucks over 24 hours, assuming the productivity remains consistent. Given that each truck costs 1650 rupees/hour, compute the cost-effectiveness.
Remember to factor in continuous usage and total output.