Define float in project management.
Think about how it relates to the start and finish times.
What is the critical path?
Remember, it involves activities with zero float.
What does float refer to in project management?
Think about how it relates to critical tasks.
True or False: The critical path is determined by activities with the least float.
Consider what zero float means.
A construction project requires cranes for four activities (A, B, C, D) with durations of 3, 4, 2, and 5 days respectively, and critical floats of 0, 3, 0, and 1 days. Describe the allocation process.
Focus first on activities with zero float.
Explain how delays in critical activities affect the overall project timeline when resource constraints are imposed.
What is the nature of critical paths?